Guide rail 2-leaf

TS 5000 R-ISM ECline * Overhead door closer system with guide rail for barrier-free, easy-to-open double leaf doors with closing sequence control and smoke switch control unit

Door closer system TS 5000 R-ISM/0 SoftClose / ECline with HM Overhead door closer with guide rail system for double leaf doors with closing sequence control, smoke switch and integrated back check, which brakes heavily applied doors.
  • System with two door closers TS 5000 ECline, R-ISM guide rail
  • Closing force of EN 3-5 with variable adjustment
  • Operating voltage 230 V AC
  • Can be used for right and left hand doors without conversion
  • Integrated smoke switch control unit, whose signal closes the door automatically in the event of a fire
  • Smoke switch with contamination indicator and adaption of the alarm threshold
  • Additional smoke detectors can be fitted
  • Electric hold-open device in the guide rail on both leaves with hold-open area 80°-130°
  • Hydraulic latching action which accelerates the door shortly before it is closed
  • Closing speed can be individually adjusted
  • Integrated back check, slows down doors that are thrown open forcefully
  • Visual closing force display for easy control of the setting
  • All functions can be adjusted from the front
  • Query that the door leaf is held open via a potential-free contact on the electric hold-open device
Contact us

Application Areas

  • Fire and smoke protection doors
  • Right and left double leaf single-action doors
  • Single-action doors up to 2500 mm hinge clearance and 1250 mm leaf width
  • Symmetrical and asymmetrical division of door possible
  • Door leaf installation hinge side
  • Hold-open systems with integrated hold-open device

Technical data

TS 5000 R-ISM ECline
Closing force in accordance with EN 1154 EN 3 - 5
Barrier-free in accordance with DIN 18040 up to leaf width (max.) in mm 1250 mm
Leaf width (max.) 1250 mm
Type of installation Door leaf installation hinge side
Opening angle (max.) 180 °
Input voltage 230 V AC
Frequency of supply voltage 50 Hz
Minimum hinge clearance 1500 mm
Minimum passive leaf width 400 mm
Suitability for fire protection doors Yes
Closing force adjustable Yes, stepless
Adjustable closing speed Yes
Latching action adjustable Yes, via valve
Back check integrated Yes, hydraulically adjustable
Position of closing force adjustment Front
Visual closing force display Yes
Hold-open function Electrical
Hold-open device on the active leaf / passive leaf Yes / Yes
Hold-open range 80 ° - 130 °
Smoke switch integrated Yes
Closing sequence control integrated Yes

Downloads

Product shot

Product data sheet

Installation instructions

Wiring diagram

Certificate

Supplementary sheet

Flyer/folder

Product brochure

Declarations of performance

Environmental declaration

3D model

Installation drawing

Variants & Accessories

Contact

Centrala GEZE Polska +48-224-404-440 GEZE Service +48-224-404-450